Residential License # 890459
Commercial License # 3667
Talk to an Expert
Stamped concrete and interlocking pavers can both make an attractive patio in the New Orleans area, and they behave very differently once they are in the ground. A typical stamped patio is a poured slab divided by planned joints, and concrete has an inherent tendency to crack. Pavers are individual units set on sand and a compacted base, so a section can be lifted and reset. This guide compares the two on the issues that matter in South Louisiana yards: settling soils, heavy rain, cracking, repairs, sealing and slip resistance.
Most of the land in the New Orleans metro area is slowly sinking, according to the City of New Orleans NOLA Ready subsidence page. The page describes subsidence as the settlement of organic soils or of saturated mineral soils of very low density, and it explains that shallow subsidence generally results from drying and shrinkage, or oxidation of organic material, after drainage. It also notes that houses not built on deep pilings are experiencing differential settlement and cracking, and that the entire region is subject to subsidence at rates that vary across space and time.
Conditions vary from one lot to the next, so no single rule fits every yard. Soft soil, settlement and standing water all affect how a patio performs over time, which is why base preparation and drainage deserve as much attention as the surface you pick. If you are still comparing patio surfaces more broadly, our guide to patio paving materials for New Orleans summers covers travertine, brick, flagstone and permeable pavers.
Stamped concrete is generally poured concrete that is colored and textured with a pattern, often to resemble stone, brick or tile. It is still concrete, so general concrete guidance applies. The National Ready Mixed Concrete Association’s guidance on cracking states that all concrete has a tendency to crack and that it is not possible to produce completely crack-free concrete. It lists improper jointing, improper subgrade preparation, too much water in the mix, improper finishing and inadequate curing among the common causes of cracks.
Joints are how concrete contractors control where cracks form. NRMCA’s guidance on joints describes joints as pre-planned cracks and recommends a maximum joint spacing of 24 to 36 times the slab thickness, which works out to about 10 feet for a 4-inch slab, with spacing limited to a maximum of 15 feet. NRMCA also notes that most random cracks that appear at an early age, although unsightly, rarely affect the structural integrity or service life of concrete. On a decorative patio, even a harmless crack changes the look, so joint layout matters for appearance as well as performance.
On soft or settling ground, the work under the slab matters. NRMCA recommends removing topsoil and soft spots, compacting the soil or granular fill beneath the slab, and sloping the slab and subgrade for proper drainage. Ask any concrete contractor how they plan to prepare the base, where the joints will go and how the patio will shed water.
Interlocking concrete pavers are set on a compacted aggregate base and a layer of bedding sand, with sand filling the joints. The Interlocking Concrete Pavement Institute’s construction specification explains that the pavers interlock and transfer loads to surrounding pavers through the joint sand, and that, unlike concrete or asphalt, they do not rely on continuity of their material for structural integrity. As a result, sections can be removed to reach underground utilities or correct local problems in the base, then reinstated using the same pavers.
Pavers still need a well-built base. ICPI’s Tech Spec 2 says patios and pedestrian areas should have a minimum base thickness of 4 inches after compaction over well-drained soils, and that base thickness is determined by traffic, soil type, subgrade drainage and moisture, and climate. It calls compaction of the soil subgrade critical and says adequate compaction will minimize settlement. Where soil remains saturated part of the year, or over clay and moist silty soils, ICPI says a geotextile may be used under the base to keep soil from migrating into the aggregate.
Drainage is part of the design too. ICPI recommends slopes of at least 1.5 percent and removing free-standing water from saturated soil during excavation, and it recommends perimeter drain pipes in clay or other slow-draining soils subject to vehicular traffic. For a patio, ask your installer how water will leave both the surface and the base.
With pavers, ICPI describes lifting and reinstating the same units to reach and fix problems below the surface, so an area that has settled can be taken up, the base corrected and the pavers put back. ICPI also notes that stabilized joint sand may have advantages in areas prone to joint sand loss, which is worth discussing if your patio sits where runoff concentrates.
With stamped concrete, the ASCC Decorative Concrete Council notes that as sealer wears, color loses intensity, which could contribute to appearance differences between areas with different sealer conditions. If a uniform appearance matters to you, ask a contractor to show you examples of repaired stamped surfaces before you commit.
Sealer is part of owning stamped concrete. The ASCC Decorative Concrete Council’s sealer selection and application guide states that no decorative concrete installation is complete without a sealer, and it describes the sealer as a sacrificial coat that will show wear and eventually need reapplication. Timing varies with exposure and traffic, and as a general rule of thumb the guide suggests new sealer every 2 to 3 years for higher traffic and UV-exposed areas.
Humidity matters when you reseal. The same guide says that above 70 percent relative humidity, concrete sealers take longer to dry, and that high humidity during application and drying of a water-based sealer may cause it to dry with a white appearance or chalky consistency. It recommends waiting for humidity below 70 percent before applying a water-based sealer. In the New Orleans area, that makes it worth scheduling a reseal around the weather.
Traction deserves attention on any patio that gets wet. The ASCC guide says slip resistance must be addressed during the initial sealer application and every reseal, that grit additives can be mixed into the sealer, and that grip additives do not make a surface totally non-slip. NRMCA recommends a broom finish for better traction on exterior concrete surfaces. For pavers, ICPI’s construction specification notes that chamfered joints help remove surface water. Whichever you choose, ask how the finished surface performs when wet.
Cost depends on size, pattern, base work and site conditions, so compare written quotes that spell out base depth, drainage and joint layout. Check with the permit office that covers your address before work starts. For a local example, see our post on patio paving in Hammond, or read about custom patio costs in New Orleans.
TurnKey Patio offers patio paving and custom patio design and installation for homeowners in New Orleans and our surrounding service areas, including Hammond, Metairie, Kenner, Mandeville, Covington and Slidell. We benefit if you hire us, and the questions above are worth asking whoever builds your patio. Call (504) 285-2824, Monday through Friday from 8:00 AM to 3:00 PM, or request a free estimate.
It depends on the site and the installation. Pavers are individual units that interlock through joint sand, so ICPI notes sections can be removed and reinstated when the base needs work. A typical stamped-concrete patio is a poured slab divided by planned joints, and NRMCA notes that all concrete tends to crack, with improper subgrade preparation among the common causes. Because the City of New Orleans says the entire region is subject to subsidence, ask any installer how they will prepare, compact and drain the base.
Some cracking should be expected. NRMCA states that all concrete has a tendency to crack and that completely crack-free concrete is not possible. Properly spaced joints help control where cracks form, and NRMCA recommends a maximum joint spacing of 24 to 36 times the slab thickness, or about 10 feet for a 4-inch slab. It also notes that most random cracks that appear early rarely affect structural integrity or service life.
It varies with sun exposure and traffic. The ASCC Decorative Concrete Council gives a general rule of thumb of every 2 to 3 years for higher traffic and UV-exposed areas, and it lists faded areas and blotchiness, especially when the surface is wet, as signs a surface needs new sealer. Follow the sealer manufacturer’s directions, and avoid applying a water-based sealer when humidity is above 70 percent.
Yes, in many cases. ICPI explains that because interlocking pavers do not rely on continuity of their material for structural integrity, sections can be removed to correct problems in the base or reach utilities, then reinstated using the same pavers.
Check with the permit office that covers your address before work begins, and ask your contractor who will handle any required permits.